What do construction delays really cost and how can you avoid them forever?

You’re considering building a new warehouse or production hall. Your first task: run the financial exercise. To get a realistic view of the total costs, it’s crucial to also account for any additional costs linked to construction delays. In this blog, discover what such delays could cost your company and, more importantly, how we at Veldeman eliminate them for good.

The additional costs of construction delays

In traditional construction projects, such as concrete or steel buildings, a delay of several weeks or even months is unfortunately not uncommon. The potential financial damage? It often turns out to be higher than you might initially think. Some cost items that are rarely included in the first calculation:

  • Production downtime: a line that isn’t running generates no revenue;

  • Extra logistics costs: external storage means additional expenses and coordination;

  • Inefficient staffing: personnel are ready but cannot start work;

  • Penalties or claims from suppliers or clients;

  • The domino effect: other departments or even projects get delayed as well.

The usual culprits

Construction delays are often caused not only by execution but also by preparation issues:

  • Waiting for permits that take longer than expected;

  • Foundations that prove insufficient and require adjustments (and recalculations);

  • Certain elements of the original design or execution no longer meet expectations, leading to extra work;

  • A subcontractor missing deadlines, delaying the entire project;

  • Delayed delivery of certain materials;

  • Weather causing weeks of downtime during the shell construction phase;

Whatever the cause, waiting times and costs inevitably keep mounting.

A cost example

Suppose you are building a new production hall, with an investment of €8 million and a construction period of 12 months.

  • In theory, this corresponds to a project value of around €32,000 per working day;

  • One week of construction delay would then translate into €160,000 in investment losses – your building generates a week less of return;

  • On top of that, there are daily operational losses due to the costs mentioned above, such as idle machines, delayed deliveries, contractual penalties, etc.

In this example, the daily cost of a delay could reach €50,000 per day or even more. A fast and flawless construction process is therefore crucial, especially in sectors like manufacturing, logistics, or food, where every day counts.

storage tent structure Veldeman
Our temporary structures and long-term demountable buildings are specifically designed to be assembled quickly and put into operation in no time.

What if you could turn a delay into an acceleration?

At Veldeman, we take a different approach to industrial and logistics construction. Our temporary structures and long-term demountable buildings are specifically designed to be built and operational in record time. No months of preparation or complex site planning – just speed and certainty.

Here’s a comparison of the decisive factors that immediately impact construction time and expected total costs:

 

  Classic construction Veldeman structure
Permits required Yes Usually not
Foundations Yes None or minimal
Construction time Several months A few days to weeks
Scalability Difficult Modular and flexible
Relocatable No Yes
Operational costs High Low
Total cost of ownership  €  €  €  €  €

 

With widths of up to 50 meters and heights up to 6 meters, our tent structures can cover enormous areas. Need something bigger? We can create a fully customized design thanks to our in-house design team and the scalability of our construction elements. Additionally, you have all the finishing options available that a traditional industrial building would provide.

storage veldeman tent structure
With widths of up to 50 meters and heights of up to 6 meters, our tent structures can cover vast areas. Need more? We can create a fully customized solution.

Time is money (and certainty means profit)

The exact cost of a construction delay depends on the project. But for those who want to play it completely safe, a flexible construction solution is the best choice. Flexibility equals long-term certainty, and certainty means no unnecessary costs, only immediate profit.

Want to avoid your project being delayed by months, with all the associated costs? Discover which Veldeman solution is the best fit for your construction plans: a temporary structure or a long-term demountable building.

Take the testCompose your own structure

demontabel gebouw Veldeman

Questions for a Veldeman advisor

Our professionals think along with you and are happy to shape your plans.